News Flash

Posted on: June 29, 2022

Stark County Engineer Keith A Bennett Announces Pittsburgh Ave Closing for 100 days

Under ConstructionGRAPHIC

Pittsburgh Avenue in Jackson Township will be closed to through traffic starting Tuesday, June 28 for one hundred (100) days. The closure will be on Pittsburgh Avenue immediately north of Orion Street. Traffic must re-route using Orion Street, Pittsburgh ...

Read on...

Additional Info... Construction
Posted on: April 8, 2022

City of Green Begins 2022 Street Resurfacing Project in May

Under ConstructionGRAPHIC

GREEN, OH – As the City of Green begins its annual street resurfacing project, the Engineering Department would like to inform residents of what is expected. The city is working on repaving select streets starting mid-May.

The areas that are scheduled for ...

Read on...

Construction

News Flash

Posted on: July 21, 2022

July 21, 2022 EPA Update: Focused Investigative Area Identified

Of the 55 wells tested in Green, 1-4 dioxane levels were detected in 16 primary wells.  As of July 20, 4 homes have been converted to a public water supply. Three more are in the process of connecting to public water.

The testing area has been ide...

Read on...

EPA Updates
Posted on: June 2, 2022

June 2, 2022: Update from EPA Investigation at Industrial Excess Landfill

Summit County Public Health Logo

Update from EPA Investigation 1,4-Dioxane Groundwater Investigation at Industrial Excess Landfill in Uniontown, Ohio

June 2, 2022 (GREEN, OH) -- The City of Green has been notified by the US EPA that some wells in the investigation area within Green have ...

Read on...

Additional Info... EPA Updates
Posted on: May 24, 2022

EPA conducts 1,4-dioxane groundwater investigation at Industrial Excess Landfill in Uniontown, Ohio

EPA conducts 1,4-dioxane groundwater investigation at Industrial Excess Landfill in Uniontown, Ohio 

[Green, OH] –The U.S. Environmental Protection Agency (EPA) is currently overseeing a groundwater investigation for 1,4-dioxane west of ...

Read on...

EPA Updates

News Flash

Home

14 Stories
Posted on: September 27, 2022

PUBLIC NOTICE: Kreighbaum Park Input and Feedback Meeting

City of Green fox mascot newsflash

Kreighbaum Park Neighborhood Input and Feedback meetingWednesday, October 5 at 6 pm or Saturday, October 8 at 10 am.Kreighbaum Park, 3143 Kreighbaum Road                   &a...

Read on...

Home
Posted on: September 29, 2022

City of Green Accepting Applications for its Spring 2023 Green Community Leadership Initiative Class

Green Community Leadership Initiative

 

City of Green Accepting Applications for its Spring 2023 Green Community Leadership Initiative Class

GREEN, Ohio – The City of Green is currently accepting applications for the Spring 2023 Green Community Leadership Initiative Class. &a...

Read on...

Additional Info... Home
Posted on: September 26, 2022

From Costumes to Candy, The City of Green Has Your Halloween Activities Covered

Green Ohio Logo

From Costumes to Candy, The City of Green Has Your Halloween Activities Covered

GREEN, Ohio – Please join the City of Green throughout the month of October to celebrate Halloween with a variety of events. Halloween events include the monthly Todd...

Read on...

Home
Posted on: September 15, 2022

City of Green joins Power A Clean Future Ohio

Green Ohio Logo

City of Green joins Power A Clean Future Ohio

(GREEN, OH)— At the September 13, 2022 Green City Council meeting, council members voted unanimously to adopt a resolution joining Power a Clean Future Ohio. Power A Clean Future Ohio is a no...

Read on...

Home
Posted on: September 2, 2022

Parker's Trail Challenge Kicks off on September 10 at The Mindfulness Walk Dedication Event

Park Ranger

Parker's Trail Challenge Kicks off on September 10 at The Mindfulness Walk Dedication Event 

GREEN, Ohio – Join the community of Green to pause, reflect, and breathe on Saturday, September 10 at 10 a.m. at Southgate Park for the...

Read on...

Additional Info... Home
Posted on: May 11, 2022

City Council to Discuss Proposed Property Maintenance Code Final Draft

Green Ohio Logo

UPDATE: City Council will meet to discuss the final draft of the proposed property maintenance code at the 5 p.m. committee meeting on 9/27. Public hearing to be scheduled for a later date.

The next committee meeting discussing the proposed code is schedul...

Read on...

Home
Posted on: August 9, 2022

Final Stages of the Greensburg/Arlington Road Roundabout Project includes two separate road closures

Under ConstructionGRAPHIC

Final Stages of the Greensburg/Arlington Road Roundabout Project includes two separate road closures beginning August 22 with the closure of Arlington Road between Greensburg and E. Nimisila  

GREEN, OH – Closures related to the Arlingto...

Read on...

Additional Info... Home
Posted on: August 23, 2022

City of Green Drug Task Force to Dedicate the Mindful Walk at Southgate Park on Sept. 10

Drug Task Force logo

City of Green Drug Task Force to Dedicate the Mindful Walk at Southgate Park on Sept. 10

GREEN, OH—Pause. Reflect. Breathe. Join the community of Green to pause, reflect and breathe on Saturday, September 10 at the dedication of Green’s...

Read on...

Additional Info... Home
Posted on: July 28, 2022

City of Green Offers an Array of Activities for Green Seniors (50+)

Green Ohio Logo

GREEN, OH – This fall the City of Green is offering many new programs and special events for Green seniors and active adults (50+). Look forward to events including bus trips, monthly lunches, game night, the annual City of Green Senior Expo and Senior Ho...

Read on...

Additional Info... Home
Posted on: July 21, 2022

Announcing the Student Municipal Representative Class of 2022-2023

Green Ohio Logo

GREEN, Ohio – Mayor Gerard Neugebauer is pleased to announce the City of Green’s 2022-2023 Class of Student Municipal Representatives. Thirty Green high school students will serve as non-voting members on boards and commissions Septemb...

Read on...

Additional Info... Home
Posted on: June 24, 2022

Improving Infrastructure and Traffic Congestion: Massillon Road South Corridor

241South_CorridorImprove_Logo

GREEN, OH – Construction of the Massillon Road South corridor project will begin this July. The project will improve the safety and efficiency of two intersections, at Boettler Road and Corporate Woods Circle, by replacing the traditional signaled interse...

Read on...

Additional Info... Home
Posted on: April 25, 2022

City of Green Releases Future Concepts for the Community Courts

Community Courts Floor Plan

The City of Green releases an initial space layout concept for the Green Community Courts. The proposed facility will be built by the city on Green Local School property in concert with the new school facilities plan being presented to voters as Issue 3 o...

Read on...

Community Courts Input Form Home
Posted on: May 16, 2022

EPA Conducts 1,4-dioxane groundwater investigation at Industrial Excess Landfill in Uniontown

On Wednesday, May 11, the EPA reached out to the City of Green to notify us that they are continuing their investigation and testing of wells in the area west and northwest of the Industrial Excess Landfill Superfund site in Uniontown, east of Cleveland A...

Read on...

Additional Info... Home
Posted on: March 30, 2022

Mayor Gerard Neugebauer Seeks Letters of Interest for Open Position on Living Green Task Force

Green Ohio Logo

GREEN, OH – The City of Green’s Mayor Gerard Neugebauer is accepting letters of interest from Green residents and members of the business and non-profit community who are interested in serving on the city’s Living Green Task ...

Read on...

Additional Info... Home

News Flash

News Flash

Posted on: November 23, 2021

November 23, 2021 -- Massillon Road North Complete

Remember to yield to all lanes of traffic in a multi-lane roundabout. 

Additional Info... Massillon Road North Updates
Posted on: September 28, 2021

September 27: Final Paving of Massillon Road North

The final paving of Massillon Road north begins the week of September 27. Paving and striping will be take a week or so to complete.

Additional Info... Massillon Road North Updates
Posted on: March 24, 2021

March 24, 2021: Phase 3 Begins March 29

On Monday, March 29, phase 3 of the Massillon Road North Project begins. Traffic at the intersection of of Massillon Road and SR619 will be shifted to redefined lanes with no dedicated turn lanes. Sheriff deputies will direct traffic while this shift take...

Read on...

Additional Info... Massillon Road North Updates
Posted on: January 21, 2021

January 18, 2021 Construction Progresses through Winter Months

The week of January 18 crews began work on installing new water mains along Massillon Road near SR619. Lanes will be restricted with traffic maintained. Please anticipate delays. The work should last 2 weeks. 

Additional Info... Massillon Road North Updates
Posted on: October 2, 2020

October 2, 2020 - Project Update

Beginning Monday, Oct. 5, Raber Road at Massillon Road in Green will be closed for 45 days. In addition, traffic will be moved to the newly constructed pavement and roundabouts on Massillon Road.  Motorists are urged to use caution when traveling...

Read on...

Additional Info... Massillon Road North Updates
Posted on: September 28, 2020

Project Update -- September 28, 2020

Businesses in the corridor, download the following info and share with your employees, visitors, clients and customers. 

Overview graphic of the construction area

Roundabout Driving Details

Raber Road Detour Map

Frequently Asked Questions 

Si...

Read on...

Massillon Road North Updates
Posted on: September 24, 2020

September 24, 2020 -- Project Update

Directional signage

Beginning October 2, weather permitting, Raber Road will close for 45 days. Stein Road will also close for 45 days. Traffic will move onto the new pavement and roundabouts on Massillon Road. Traffic will be maintained on Massillon Road.  

Posted d...

Read on...

Additional Info... Massillon Road North Updates
Posted on: September 16, 2020

Project Update -- September 16, 2020

Raber Road Roundabout

In mid-October, traffic will move from the current lanes of travel to the new pavement and roundabouts. Raber Road and Stein Road will be closed for up to 45 days when we move to the new traffic patterns. Specific dates of closure and traffic changes are ...

Read on...

Additional Info... Massillon Road North Updates
Posted on: July 14, 2020

July 14, 2020 Massillon Road North Update

Work this week continues with installation of storm sewers along Raber Road and Stein Road. A new water main along Raber and Massillon Road will begin being installed.  With the next week, new traffic patterns will be set up along Massillon Road....

Read on...

Additional Info... Massillon Road North Updates
Posted on: July 6, 2020

July 6, 2020 Massillon Road North Update

This month, crews from Karvo Companies will continue work on what will become the southbound lanes of Massillon Road. They will be setting up a defined construction zone running along the west side of Massillon Road to help keep crews safe. Crews are addi...

Read on...

Massillon Road North Updates

News Flash

Posted on: August 22, 2022

Traffic Light Changeover at Massillon/Corporate Woods Circle on August 23

Sheriff Deputy will direct traffic on Massillon Road at the Corporate Woods Circle and Thorn Drive intersection on August 23 from 8:30 a.m. to 2 p.m. as the contractor switches over to the temporary traffic signal. Expect delays. 

Read on...

Additional Info... Massillon Road South
Posted on: August 1, 2022

Franks Parkway West Bound Lanes Closed from CVS Drive to Massillon Road

241South_CorridorImprove_Logo

Franks Parkway west bound lanes between Massillon Road and CVS Drive will be closed beginning Tuesday, August 2 for two weeks, weather permitting.  The closure is required to install a boxed culvert. Access from ACME and surrounding plaza busines...

Read on...

Massillon Road South
Posted on: July 14, 2022

Construction Begins Monday, July 18

241South_CorridorImprove_Logo

The contractor will begin on Franks Parkway (east of Massillon Road) installing a boxed culvert. The right turn lane from Franks onto Massillon will be closed. Traffic will be maintained in all directions the week of July 18. 

Read on...

Additional Info... Massillon Road South