News Flash

Posted on: November 23, 2021

November 23, 2021 -- Massillon Road North Complete

Remember to yield to all lanes of traffic in a multi-lane roundabout. 

Additional Info... Massillon Road North Updates
Posted on: September 28, 2021

September 27: Final Paving of Massillon Road North

The final paving of Massillon Road north begins the week of September 27. Paving and striping will be take a week or so to complete.

Additional Info... Massillon Road North Updates
Posted on: March 24, 2021

March 24, 2021: Phase 3 Begins March 29

On Monday, March 29, phase 3 of the Massillon Road North Project begins. Traffic at the intersection of of Massillon Road and SR619 will be shifted to redefined lanes with no dedicated turn lanes. Sheriff deputies will direct traffic while this shift take...

Read on...

Additional Info... Massillon Road North Updates
Posted on: January 21, 2021

January 18, 2021 Construction Progresses through Winter Months

The week of January 18 crews began work on installing new water mains along Massillon Road near SR619. Lanes will be restricted with traffic maintained. Please anticipate delays. The work should last 2 weeks. 

Additional Info... Massillon Road North Updates
Posted on: October 2, 2020

October 2, 2020 - Project Update

Beginning Monday, Oct. 5, Raber Road at Massillon Road in Green will be closed for 45 days. In addition, traffic will be moved to the newly constructed pavement and roundabouts on Massillon Road.  Motorists are urged to use caution when traveling...

Read on...

Additional Info... Massillon Road North Updates
Posted on: September 28, 2020

Project Update -- September 28, 2020

Businesses in the corridor, download the following info and share with your employees, visitors, clients and customers. 

Overview graphic of the construction area

Roundabout Driving Details

Raber Road Detour Map

Frequently Asked Questions 

Si...

Read on...

Massillon Road North Updates
Posted on: September 24, 2020

September 24, 2020 -- Project Update

Directional signage

Beginning October 2, weather permitting, Raber Road will close for 45 days. Stein Road will also close for 45 days. Traffic will move onto the new pavement and roundabouts on Massillon Road. Traffic will be maintained on Massillon Road.  

Posted d...

Read on...

Additional Info... Massillon Road North Updates
Posted on: September 16, 2020

Project Update -- September 16, 2020

Raber Road Roundabout

In mid-October, traffic will move from the current lanes of travel to the new pavement and roundabouts. Raber Road and Stein Road will be closed for up to 45 days when we move to the new traffic patterns. Specific dates of closure and traffic changes are ...

Read on...

Additional Info... Massillon Road North Updates
Posted on: July 14, 2020

July 14, 2020 Massillon Road North Update

Work this week continues with installation of storm sewers along Raber Road and Stein Road. A new water main along Raber and Massillon Road will begin being installed.  With the next week, new traffic patterns will be set up along Massillon Road....

Read on...

Additional Info... Massillon Road North Updates
Posted on: July 6, 2020

July 6, 2020 Massillon Road North Update

This month, crews from Karvo Companies will continue work on what will become the southbound lanes of Massillon Road. They will be setting up a defined construction zone running along the west side of Massillon Road to help keep crews safe. Crews are addi...

Read on...