Massillon Road South

  1. Massillon Road South Project Traffic Pattern Changes June 8

    GREEN, OH – The evening of June 8, the Massillon Road South infrastructure project moves to Phase 2 to construct the west side of road. Traffic patterns will change. Read on...
  2. Massillon Road Phase 1 Paving Begins Week of May 1

    CONSTRUCTION ALERT: Massillon Road south paving of Phase 1 begins the week of May 1. Read on...
  3. Massillon Road Construction Changes to Traffic Pattern on November 1

    CONSTRUCTION UPDATE: On Tuesday, November 1 (weather depending), the contractor will changeover to a new traffic pattern for the next phase of construction on Massillon Road South. Read on...
View All

Navigating the Corridor During Construction

241South_CorridorImprove_Logo

Project Overview

Construction of the Massillon Road South corridor project will begin this July. The project will improve the safety and efficiency of two intersections, at Boettler Road and Corporate Woods Circle, by replacing the traditional intersections with roundabouts. CVS Drive will also be extended to connect Franks Parkway to Thorn Drive. Street lighting and landscaping will be added to enhance the corridor. Construction is expected to be completed in November 2023. 

Maintenance of Traffic

North and South bound traffic on Massillon Road will be maintained throughout the duration of the project. However, there will be periods of closure for all intersecting roadways.  

Construction Dates

Anticipated to begin in July 2022. Completion date is November 2023. 